Regular overhaul was performed at Electric Desalting Plant ELOU-AT-2 on April 31-May 14, 2014. Over 100 specialists took part in the works, namely, the organization departments of the Oil Refinery: Oil Refining Shop No. 1, Mechanical Supervisor’s Service, Chief Power Engineer’s Service, Chief Metrologist’s Service, and Logistics Department. Besides, several companies: SK Techinzhstroy and EPB-Servis, performed the works on a contractual basis.

The following works and tests were performed: hydraulic pressure testing of column, heat-exchange equipment and tanks of Electric Desalting Plant ELOU-AT-2 (with the stopping of the plant), inspection and calibration of the valves, and replacement of the sealing materials of the processing equipment surfaces, as well as other works under the project “re-equipment and technical upgrading of Refining Shop No. 1 (Electric Desalting Plant ELOU-AT-2)” developed by the engineering design department of Antipinsky Oil Refinery are scheduled for.

The next repairs at Antipinsky Oil Refinery are scheduled for October 2016 and will be performed at the Hydrogen Unit, Diesel Oil Hydrotreating Unit, Elemental Sulfur Unit and Bulk Nitrogen and Air Supply Unit.

Back to the list

Other news