2005 Results

1 January 2005

January 23, 2005

General Designer Neftekhimproekt OJSC completed the drawing up of design and estimate documentation needed for the construction. The process of amending the engineering aspect of the design is nearing completion. 

February 9, 2005

The General Contractor, Tyumenpromstroi Building Company started the works on the refinery’s site. 

May 19, 2005

The General Contractor started the installation of technological equipment. 

May 24, 2005

The production facilities have been built, the construction and assembly works at the water supply and sewage systems networks have been completed.

June 12, 2005

The crude distillation unit of the first phase has been installed. 

June 18, 2005

Additional equipment delivery agreement has been reached with Petrofac company.

July 21, 2005

The core process equipment is completely installed.

August 15, 2005

Governor Sergei Sobyanin of the Tyumen Region visited the refinery.

August 19, 2005

Last week the laying of main motor roads on the territory of the enterprise was completed what will ensure a stable transit of technology in the autumn and spring seasons.

September 10, 2005

The finishing of the administration and on-site facilities has been completed. The administrative personnel of the refinery has moved to a new building.

September 18, 2005

Pad work for the tank battery has been completed. More than 28 thousand cum of sand have been supplied.

October 19, 2005

The General Contractor got down to the construction of the tank battery.

Back to the list